Updated CSO Control Plan

Planning & Engagement Timeline

The April 30, 2026 Draft followed more than four years of technical development, regulatory coordination, public meetings, watershed engagement, community outreach, and written input. MWRA, Cambridge, and Somerville are the CSO Planning Partners responsible for the joint Draft. The public comment period remains open through October 30, 2026.

New to CSOs? A combined sewer overflow (CSO) can occur when wet weather overwhelms an older combined sewer system carrying sewage and stormwater in the same pipes, causing excess flow to discharge to a nearby waterway. Start with the CSO Resources Hub.
4+Years of Plan DevelopmentFormal process began in 2022
6Pre-Draft Public MeetingsPlus a dedicated Listening Session
6Watershed MeetingsIncluding focused notification meetings
29Community EventsPublished outreach count
19EPA / MassDEP MeetingsReported during Draft development
Timeline at a glance

Public review now underway after more than four years of plan development

4+ years developing the Draft

Technical work, alternatives evaluation, affordability analysis, regulator coordination, and public engagement all fed into the April 2026 filing.

6 Public Meetings 6 Watershed Meetings 29 Community Events 19 EPA / MassDEP Meetings 7 Surveys & Questionnaires
Draft public review

Public Meeting #7, office hours, hearings, library copies, and written comments continue the review after filing.

Final Plan preparation

Comments are reviewed and the Final Updated CSO Control Plan is prepared for January 31, 2027.

Overview segments are weighted for readability; milestone dates above show the actual schedule.

Full record

Planning and Engagement Over Time

  • Major milestones remain visible throughout the timeline.
  • Select one or more filters to emphasize different forms of engagement.
ShowColor + icon legend · select one or more
2021 · RELATED PRECURSOR
September 2021

Somerville High School Outreach

Presentations on combined and separated sewer systems and citywide flooding.

Related precursor outreach
2022
April 1, 2022

Formal Updated CSO Planning Begins

MWRA, Cambridge, and Somerville submit Updated CSO Control Plan scopes to MassDEP and EPA.

June 29, 2022

Public Meeting #1

Introduction to the planning process and schedule.

226 participants recorded
July 22, 2022 · MassDEP approves the submitted planning scopes.
December 15, 2022

Public Meeting #2

Project goals, approach, and development of the future 2050 Typical Year.

177 participants recorded · 86 questionnaire responses
2023
2022–April 2026

Recurring EPA / MassDEP coordination

The Partners report ongoing agency coordination throughout Plan development.

19 meetings reported
Throughout 2023

Community-Event Outreach Expands

Project information is shared at events including CX Summer Nights, July 4th Pops, the Cambridge 5K, and other community activities.

Multiple documented outreach events
2023 · Climate-informed Typical Year, unified modeling, technology screening, and evaluation criteria develop.
October 24, 2023

Watershed Advocacy Meeting #1

CSO-control technologies, future rainfall modeling (the 2050 Typical Year), and preview of Public Meeting #3.

21 participants recorded
November 15, 2023

Public Meeting #3

Technology toolbox and stakeholder values used to help develop evaluation criteria.

243 participants recorded · 81 live-survey responses
December 12, 2023–January 15, 2024

Open Questionnaire Following Public Meeting #3

A month-long public questionnaire collected additional input following the meeting.

1,312 responses
2024
June 24, 2024

Watershed Advocacy Meeting #2

Alternatives-development process, tools under consideration, and mapping exercise.

32 participants recorded
Throughout 2024

Community Outreach Continues

Outreach continues at Fresh Pond Day, Cambridge Arts River Festival, SomerStreets, Pride Flotilla, and other documented events.

Multiple documented outreach events
August 30 / September 1, 2024

New Five-Year CSO Variances Issued and Take Effect

The Variances formalize Updated Plan requirements, public participation and environmental justice outreach, affordability analyses, and Draft/Final Plan milestones.

November 20, 2024

Focused Watershed Meeting — Real-Time Notification

Input on notification in flood-prone areas and the feasibility-study scope.

25 participants recorded
December 17, 2024

Watershed Advocacy Meeting #3

Alternatives progress, cost assumptions, and preview of Public Meeting #4.

35 participants recorded
2025
January 22, 2025

Public Meeting #4

Alternatives development and affordability methodology.

355 participants recorded · 167 live-survey responses
April 3, 2025

Dedicated Listening Session

Designed specifically to solicit concerns, advice, and priorities.

173 participants recorded · 88 survey responses
May 5, 2025

Focused watershed meeting — notification

Notification requirements, research findings, options, and public education.

20 participants recorded
Mid-2025 · Affordability analysis, review and narrowing of project alternatives, water-quality modeling, scoring, and siting continue.
Spring–Fall 2025

Continued Community-Event Outreach

Run of the Charles, Port Arts Festival, Dragon Boat Festival, Pride Flotilla, July 4th Pops, CX Summer Nights, SomerStreets, and other documented activities.

Multiple documented outreach events
September 4, 2025

Watershed Advocacy Meeting #4

Alternatives analyzed, evaluation criteria, preliminary scoring, and water-quality modeling.

29 participants recorded
September 25, 2025

Public Meeting #5

Preview of alternatives under consideration.

198 participants recorded · 70 live-survey responses
Fall 2025 · Board review, Partner cost-allocation discussions, and recommended-plan development intensify.
December 31, 2025

Original Draft Plan deadline

Shown for context. The deadline was extended 120 days to April 30, 2026.

2026
January 15, 2026

Public Meeting #6

Requested filing extension, potential recommended alternatives, water quality, construction, cost, and rate information.

359 participants recorded · 140 survey responses
April 30, 2026

Draft Updated CSO Control Plan Filed

A major milestone after more than four years of formal planning, technical analysis, regulator coordination, and engagement.

After filing

Draft Made Broadly Available

Online access plus physical copies in libraries throughout all 43 MWRA sewer-service communities and the MWRA Chelsea library.

June 2, 2026

Public Meeting #7

Draft Plan contents and how to participate in the public-comment process.

June–August 2026

Office Hours Across the Service Area

Virtual and in-person opportunities in Boston, Somerville, and Cambridge.

8 documented past sessions
August 11, 2026

Public-Comment Period Extended

MassDEP extends the deadline by 30 days, from September 30 to October 30, after public requests and consultation with the Partners.

September 17, 2026

Public Hearing #1

Hybrid hearing in Cambridge; oral comments entered into the public record.

Completed
TODAY · SEPTEMBER 24, 2026
36
Days left to commentComments close Oct. 30, 2026
How to comment
September 30, 2026

Original Public-Comment Deadline

Superseded by the 30-day extension.

October 30, 2026

Revised Public-Comment Deadline

End of the extended public-comment period.

2027
January 31, 2027

Final Updated CSO Control Plan Due

The governing 2024 Variances require submission of the Final Plan for Massachusetts Environmental Policy Act (MEPA) review.

Public & Watershed Engagement Record

A different way to inspect the record: participation and input, documented effects where the source record makes the connection, status, and source references in one place.

DateEventTypeParticipation / inputDocumented effect of inputStatusSource
Jun. 29, 2022Public Meeting #1Public meeting226 participants recorded—CompletedDraft Plan, Table 5-4
Dec. 15, 2022Public Meeting #2Public meeting177 participants recorded; 86 questionnaire responses—CompletedDraft Plan, Tables 5-4 & 5-7
Oct. 24, 2023Watershed Advocacy Meeting #1Watershed21 participants recorded—CompletedDraft Plan, Table 5-5
Nov. 15, 2023Public Meeting #3Public meeting243 participants recorded; 81 live-survey responses—CompletedDraft Plan, Tables 5-4 & 5-7
Dec. 12, 2023–Jan. 15, 2024Open Questionnaire Following Public Meeting #3Written public input1,312 responses—CompletedDraft Plan, Table 5-7
Jun. 24, 2024Watershed Advocacy Meeting #2Watershed32 participants recorded—CompletedDraft Plan, Table 5-5
Nov. 20, 2024Focused watershed meeting — notificationWatershed25 participants recorded—CompletedDraft Plan, Table 5-6
Dec. 17, 2024Watershed Advocacy Meeting #3Watershed35 participants recorded—CompletedDraft Plan, Table 5-5
Jan. 22, 2025Public Meeting #4Public meeting355 participants recorded; 167 live-survey responses—CompletedDraft Plan, Tables 5-4 & 5-7
Apr. 3, 2025Dedicated Listening SessionPublic engagement173 participants recorded; 88 survey responsesListening Session was added to the engagement framework at the suggestion of watershed advocacy groups.CompletedDraft Plan, §5.3.2.1 / Table 5-4
May 5, 2025Focused watershed meeting — notificationWatershed20 participants recorded—CompletedDraft Plan, Table 5-6
Sep. 4, 2025Watershed Advocacy Meeting #4Watershed29 participants recorded—CompletedDraft Plan, Table 5-5
Sep. 25, 2025Public Meeting #5Public meeting198 participants recorded; 70 live-survey responsesPart of additional public engagement addressing requests for greater transparency around alternatives and scoring.CompletedDraft Plan, §5.4 / Table 5-9
Jan. 15, 2026Public Meeting #6Public meeting359 participants recorded; 140 survey responsesAdditional meeting was added in response to feedback seeking greater transparency during alternatives review.CompletedDraft Plan, Table 5-4
Jun. 2, 2026Public Meeting #7Public meetingAttendance not yet lockedOpened the post-filing review phase and explained how to submit comments.CompletedJoint project page
Sep. 17, 2026Public Hearing #1Public hearing—Oral comments entered into the formal public record.CompletedJoint project page
Sep. 24, 2026Public Hearing #2Public hearing—Scheduled opportunity for oral public comment.PlannedJoint project page
Oct. 28, 2026Public Hearing #3Public hearing—Scheduled opportunity for oral public comment.PlannedJoint project page

Meeting counts are event-level participant counts from the source record; totals across events should not be read as unique people because the same person may participate more than once. Blank effect fields mean the source record does not make a direct input-to-response connection for that entry. Source links open the persistent joint-project page rather than temporary meeting URLs.